MAIN
CONSTRUCTION BEGINS
RAGTOWN
THE WORK DAY
BOULDER CITY
THE DAM RISES
DEDICATION
EARLY LAS VEGAS HOME
UNLV Libraries Digital Projects - Hoover Dam
When men were able to find work in the first phase of the dam construction it was occasionally on an auxiliary project such as building rail lines to the dam. Most men, however, found themselves working on the construction of the diversion tunnels. Before the dam could be built, the Colorado River needed to be temporarily diverted from its course. Four tunnels were planned, two on each side of the river. The most difficult part of the entire project, the construction of the diversion tunnels began May 12, 1931 and was scheduled to be completed before October 1, 1933. As Six Companies would be fined for every day the diversion tunnels went over schedule, the excavation of the tunnels proceeded at a furious pace.

When completed, the diameter of each tunnel would measure 50 feet wide, 3/4 of a mile in length. The mechanics of drilling into the solid rock walls of Black Canyon did not daunt dam foreman, Frank Crowe. Knowing that it would take countless men to make even an inch of headway into the walls, Frank Crowe came up with an idea that would allow over twenty men to drill at once. This invention, called a jumbo, consisted of rows of platforms built atop a truck. Men would stand on the platforms to drill and tamp blasts into the rock.

Diversion tunnel No. 3 on the Arizona side, Boulder Dam
Mary Eaton explains how families dealt with the temperatures
Mary Eaton explains how families dealt with the temperatures
 * Play video (12.07 MB)
 * Listen to audio only (572 KB)
0:02:21 mins.
Group of men including Frank Crowe at the dam site

Back
click either arrow to continue navigating the site
Next