Working on the diversion tunnels presented unique dangers. Not only did men have to be constantly
wary of blasting and falling rocks, they also had to deal with truck fumes. Diesel trucks were used to
haul debris out of the gradually forming tunnels. Although fans and pipes were used to circulate the air,
exhaust became trapped in the tunnels. Numerous men were diagnosed with a mysterious pneumonia. Rumors spread saying
that the men didn’t really have pneumonia but were sick from inhaling the gas fumes. Even though this was never officially proven,
dam workers were certain that the fumes were responsible for sickness among the men.
The workers did not allow threats of danger or sickness to keep them from doing their jobs. Once lights were installed
in the diversion tunnels, work was able to progress around the clock without interruption. The different work crews
competed with each other to see who could drill the most from day to day. Recognizing that the friendly competition was
having positive effects, supervisors encouraged the rivalry.
Once the tunnels had been drilled, they needed to be resurfaced with concrete. Elaborate forms and concrete guns were
used to pour cement throughout the tunnels. By November of 1932 the tunnels were finished, almost a full year ahead of schedule.
It was time to divert the river.
A cofferdam needed to be constructed to force the river into the
tunnels. Over 100 hundred trucks dropped tons of dirt, rock, and
debris into the river at a rate of one truckload every 15 seconds.
The loud and dusty process continued throughout the night. The cofferdam
was slowly built until finally it broke the surface of the water.
The river surged against the cofferdam, trying to find a way through.
As the water rose, activity on the site stilled as spectators waited
with bated breath. Early on the morning of November 14, 1932 the
Colorado was forced into the mammoth, concrete-lined tunnels. The
river had been diverted.